New Construction Timeline In Austin: Step‑By‑Step

December 11, 2025

Wondering how long a new build in Austin really takes? When you are budgeting for a new home, the difference between a smooth 6-month build and a year-plus project can feel huge. You want a clear roadmap, realistic timing, and local intel so you can plan with confidence. This guide walks you through each stage in Austin and Travis County, the typical durations, who does what, and the most common delays to watch for. Let’s dive in.

Austin new construction phases

Preconstruction and planning

Preconstruction covers land selection, financing, and design. You verify whether your lot sits inside the City of Austin or in unincorporated Travis County, confirm plat status, and check utilities and overlays. You also finalize floor plans and engineering, including energy compliance and any tree or stormwater considerations that may apply.

Municipal approvals

Inside Austin city limits, the Development Services Department reviews permits and inspections. Depending on your lot, you may only need a building permit, or you may need platting or a site plan for more complex or raw land. Utility providers such as Austin Water and Austin Energy have separate application and connection steps that can affect sequencing.

Site work and utilities

Once permits are in hand, crews clear and grade the lot, install erosion controls, and bring in utilities. In some cases, off-site utility upgrades or right-of-way improvements are required, which adds time. In Central Texas, drainage and tree protections are frequent considerations.

Vertical construction

The structure rises from foundation to finishes. Framing, roof, and windows get you dried-in, followed by rough-in of HVAC, plumbing, and electrical. After insulation and drywall, the project moves to cabinets, counters, flooring, fixtures, and appliances.

Inspections, final sign-off, and move-in

Throughout construction, municipal inspections are required at key milestones. Final city approval and utility signoffs are needed before occupancy. After move-in, builders typically complete punch-list items and honor a defined warranty.

Step-by-step timeline and durations

Pre-contract and land selection

  • Typical timing: days to months.
  • What happens: Choose a lot, confirm plat status, utility availability, easements, floodplain, and deed or HOA rules. Order a survey and consider a geotechnical report on raw land.
  • Austin note: If your lot is not already platted or needs replatting, build extra time for the subdivision process.

Financing and builder selection

  • Typical timing: 2 to 8 weeks.
  • What happens: Select a builder, secure a construction loan if needed, sign the construction contract, and align on a preliminary schedule.
  • Austin note: Lenders may review builder qualifications and local permitting history as part of approval.

Design and plan preparation

  • Typical timing: 2 to 12-plus weeks.
  • What happens: Finalize architectural plans, structural engineering, grading and drainage, and energy documentation. Custom homes trend longer than production builds.
  • Austin note: City amendments to residential codes and local tree or watershed requirements can add documentation and time.

Municipal review and permitting

  • Typical timing: several weeks to many months, depending on lot status.
  • What happens: Submit for the necessary permits. For finished lots in a recorded subdivision with utilities, a building permit is usually the key step. For raw or reconfigured land, expect platting, possible site plan review, and acceptance of public improvements.
  • Austin note: Rapid growth can extend review cycles and inspection scheduling compared with smaller markets.

Site mobilization and infrastructure

  • Typical timing: 2 to 12-plus weeks.
  • What happens: Clear and grade, install erosion controls, bring in water, sewer, and electric, and build drives or sidewalks when required.
  • Austin note: If Austin Water or Austin Energy requires off-site upgrades, coordination and construction can extend the timeline.

Foundation

  • Typical timing: 1 to 4 weeks.
  • What happens: Excavate, form, and pour the slab or install pier-and-beam systems.
  • Austin note: Central Texas soils and shallow rock often require piers or specialized foundations, which adds time and cost.

Framing and dry-in

  • Typical timing: 2 to 6 weeks.
  • What happens: Frame walls and roof, install sheathing, and set windows and exterior doors to reach dried-in status.
  • Austin note: Weather and subcontractor availability can shift sequencing.

Rough-in mechanical, electrical, plumbing

  • Typical timing: 2 to 6 weeks.
  • What happens: Run HVAC ducts, plumbing lines, electrical wiring, and gas piping. Pass municipal rough inspections before insulation.
  • Austin note: Inspection scheduling depends on city availability and can add days.

Insulation and drywall

  • Typical timing: 2 to 6 weeks.
  • What happens: Insulate to meet code and energy standards, hang drywall, tape, float, and prime.

Interior finishes and fixtures

  • Typical timing: 4 to 12-plus weeks.
  • What happens: Install cabinets, counters, trim, flooring, lighting, plumbing fixtures, and appliances.
  • Austin note: Cabinetry, countertops, windows, and HVAC equipment often drive the pace due to lead times.

Final inspections and approvals

  • Typical timing: 1 to 4-plus weeks.
  • What happens: Complete final municipal inspections and obtain city approval, along with utility signoffs as required. Walk the home, create a punch list, and schedule completion.

Move-in and warranty

  • Typical timing: 30 to 90 days is common for punch-list completion post move-in. Many builders offer a typical pattern of 1-year workmanship, 2-year systems, and 10-year structural coverage, though terms vary by builder.

Typical total timeline

  • Production or tract homes on finished lots: commonly 6 to 9 months from contract to move-in.
  • Custom homes or builds on raw or unplatted land: commonly 9 to 18-plus months. Large or complex sites can run longer if platting, site plan review, or utility extensions are required.

Permits, utilities, and local agencies

  • City of Austin Development Services Department manages building permits, plan review, inspections, tree permits, and final approvals inside city limits.
  • Austin Water handles water and wastewater availability, taps, and meter sets for city-served lots.
  • Austin Energy manages electric service applications, meter sets, and potential off-site upgrades.
  • Travis County oversees development in unincorporated areas and on-site wastewater systems where municipal sewer is not available.
  • Before you begin, request itemized estimates for impact fees, utility connection fees, and any parkland or dedication requirements applicable to your lot.

Documents to verify early

  • Plat status or replat needs, plus any site plan requirement.
  • Floodplain status and FEMA mapping that may affect the buildable area.
  • Easements, setbacks, and utility corridors that influence home placement.
  • Current survey, title commitments, and recorded deed restrictions.
  • HOA or architectural review timelines that affect when you can submit permits.

Common delays and how to avoid them

  • Municipal backlogs. Plan extra time for plan review and inspections. Ask your builder to submit early and track review cycles.
  • Utility constraints. Confirm water, sewer, and electric availability and whether mains require upgrades or extensions.
  • Geotechnical surprises. Order soils evaluations early and budget for piers or specialized foundations if needed.
  • Material and trade lead times. Lock selections with longer lead times early, such as cabinets, countertops, windows, and HVAC equipment.
  • Weather. Build contingency into site work and foundation phases, which are most weather-sensitive.
  • HOA and design review. Submit complete packages and respond quickly to avoid extra rounds.

Pro tips for a smoother build

  • Ask for a detailed schedule with milestones like permit submission, foundation, framing, drywall, finishes, and final inspection.
  • Include a realistic move-in buffer. A 6 to 12-week contingency is common on production homes, longer for custom builds.
  • Clarify responsibilities in writing. Define who pays impact and tap fees, who schedules inspections, and who orders utility connections.
  • Keep records. Save copies of permits, inspection results, and the final city approval and utility signoffs before moving in.
  • Plan housing overlap. If you are selling while building, prepare a bridge plan in case the timeline stretches.

Plan your Austin build with confidence

New construction in Austin rewards early planning and clear communication. When you understand each step, you can set expectations, keep financing aligned, and make smarter choices on design and selections. If you want a seasoned advisor who speaks both construction and market value, you are not alone.

If you are considering a new build or a custom home in the Austin area, connect with a boutique advisor who has hands-on experience across more than 200 homes. Work with Bryan Thomas Properties to align your lot, builder, budget, and timeline so you can move in with confidence.

FAQs

How long does a new Austin home build usually take?

  • Production homes on finished lots often run 6 to 9 months from contract to move-in, while custom homes or raw lots commonly take 9 to 18-plus months depending on approvals and utilities.

Who handles permits and fees for Austin new construction?

  • The builder typically submits permit applications and coordinates inspections, while payment responsibilities for impact and utility fees depend on the contract, so confirm roles in writing.

What inspections are required before I can move in within Austin city limits?

  • Expect foundation, framing, rough mechanical-electrical-plumbing, insulation, and final inspections, plus any required utility approvals before final city sign-off.

Do I need platting or a site plan for my Austin lot?

  • If your lot is already platted with utilities available, you may only need a building permit; raw or reconfigured lots often require platting and possibly a site plan, which adds months.

What foundation issues are common in Central Texas and Austin?

  • Caliche, expansive soils, and shallow rock can require engineered solutions such as piers or specialized slabs, which add time and cost to the foundation phase.

What builder warranties are typical on new Austin homes?

  • A common pattern is 1 year for workmanship, 2 years for systems, and 10 years for major structural coverage, but always verify the exact terms with your builder.

How can I protect my expected completion date in a new build contract?

  • Use defined milestones, clear force majeure language, and a documented punch-list process, and consider contingencies like move-in buffers and negotiated remedies where applicable.